Is configuration management part of change management? Or, is it the other way around?
A few months ago, there was an interesting discussion on one of the LinkedIn forum. The discussion was focused on configuration management vs change management. A few participants said that Configuration Management Plan is part of Change Management Plan. While other opined that change management plan is part of configuration management plan. Both set of participants provided their own reasons.
I think it was an entertaining discussion, but nothing more than that. One plan is not part of the other. PMBOK Guide clearly lists Configuration Management Plan and Change Management Plan as separate plans. PMBOK Guide mentions that they are subsidiary plans of Project Management Plan.
Configuration management and change management are complementary topics. Let us understand how.
Let us first understand the meaning of these terms. Sometimes, it is easier to understand the technical meanings of terms using normal dictionary. So, let us take a look at the English meanings of these terms
Table of Contents
the relative disposition or arrangement of the parts or elements of a thing.
to make the form, nature, content, future course, etc., of (something) different from what it is or from what it would be if left alone.
Let us take an example of a machine. A machine is made up of components or parts. Each part is arranged in a specific configuration to make the machine whole.
In simple terms, configuration means arrangement of the parts while change means modification of the parts or the whole machine.
Initially, a configuration (arrangement) is created. Later that configuration can be changed.
Let us look at project management meanings of configuration management and change management. I have written a post that defines terms related to change and change management. You should read that post to understand the formal definitions before reading further.
You can refer to Max Wideman’s Glossary for some standard configuration management and change management. The Project Management definitions are technically more appropriate, but the English definitions also convey the right meaning. Moreover, the English definitions are easier to understand.
At a broader level, configuration management involves following activities.
At a broader level, change management involves following activities. You can read my article 9 Rules to Answer PMP Change Management Questions to find details of these activities.
In addition to the above activities, identification of CCB members and defining authority of CCB is also done as part of the change management.
Let is analyze the above statements. The project creates many items including, but not limited to final product, product components, deliverables, documents, and work artifacts. All the items are not considered as configurable items. All configurable items may not follow a formal change management process.
Note: Many reference books and blogs have given explanation of configuration management vs change management. Some of them note that configuration management is only done for the products, which is incorrect. The PMBOK Guide clearly mentions that configuration management can be done for any type of artifact including product, product components, processes, documents, plans, and baselines.
Image courtesy of Toa55 at FreeDigitalPhotos.net
Incentive Calculation in a FPIF Contract In my previous post, I described Fixed Price Incentive Fee Contract (FPIF). In this article, I will discuss the formulas and incentive calculations for an FPIF Contract. Let me summarize the basic nature of the contract before getting into formulas and calculations. The basic nature of a FPIF Contract…
Critical Path Analysis Example – Using 0 and 1 Method I got introduced to Critical Path Analysis in the year 1997. I am a software engineer by education. I learned most of the project management concepts while managing software projects – Critical Path Analysis was one such concept. I learned about Critical Path while using…
There main difference between effort, duration and elapsed time is that effort refers to the amount of exertion or work done to complete a task, duration refers to the length of (working) time to complete a task, and elapsed time is the total amount of (working and non-working) time that passes between start of an…
Quick Reference for Earned Value Management Formulas If you are looking for a comprehensive list of all the Earned Value Management Formulas, then you are at the right place. If you are preparing for PMP® Exam, you will find all the Earned Value Formulas. This article would provide you with a step up in doing…
There are many Change and Change Management Definitions floating around. Many Project Management Standards and Leading Professionals have different Change and Change Management Definitions. Let us talk about Change and Change Management Definition as described in PMBOK Guide. This post will help you if you and your Stakeholders have frequent run-ins. It will be useful…
Lead and Lag Demystified There are many terms that perturb project management professionals. Lead and Lag are two such terms. I interact with many professionals on a regular basis. I often find that many of them are not fully aware of meaning of these terms. Even though they know the correct definitions of these terms,…
I have tried to take advantage of the discount on Joseph Phippip’s PMP training course, but I get $150. Is there a coupon code or something of this sort required?
Praveen Malik says:There is no special coupon code. You just have to click on home page ( https://www.pmbypm.com/go/udemy-homepage-promo/ ) – automatically all courses are listed as $15.
You can also buy any other course also till Sep 13 for $15.
Gregory Blank says:I think your information above is not correct:
“Configuration Management Activities
At a broader level, change management involves following activities.”
I believe you meant to say, “At a broader level, configuration management involves the following activities”
Praveen Malik says:Thanks Gregory. I appreciate. I have updated the article.
BestAngelina says:Your blog is the best alternative I have found for my PMP studies. Thank you.
Ashvini says:Thanks for posting this article & clarifying the difference between configuration & change management.
While reading the scope management chapter in PMBOK6, it is mentioned on page 137 that requirement management plan’s one of the output contains the information about Configuration management such as how changes will be analyzed, how impacts will be analyzed,how they will be tracked & reported , as well as the authorization levels required to approve these changes.
The info in the above paragraph seems to be pertaining to change management system rather than configuration management. Please correct me if there is gap in my understanding.
On the page 701 of PMBOK 6, the configuration management system is defined as A collection of procedures used to track project artifacts and monitor and control changes to these artifacts.
On the page 532 of PMBOK 5, configuration management is defined as
“A subsystem of the overall project management system. It is a collection of formal documented procedures used to apply technical and administrative direction and surveillance to: identify and document the functional and physical characteristics of a product, result, service, or component; control any changes to such characteristics; record and report each change and its implementation status; and support the audit of the products, results, or components to verify conformance to requirements. It includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes.”
In PMBOK 6’s page 88, the Change MP & Config MP is defined as follows.
Change management plan: Describes how the change requests throughout the project will be formally authorized and incorporated.
Configuration management plan: Describes how the information about the items of the project (and which items) will be recorded and updated so that the product, service, or result of the project remains consistent and/or operative.
Praveen Malik says:Thanks for sharing the PMBOK Guide’s references. I will help many other readers.
Cheryl Preston says:Thank you for this article. I also recall some discussion on LinkedIn regarding Change Management vs. Configuration Management and probably chimed in on the discussion over the years to weigh in. From my perspective, as a veteran CM practitioner, I have seen the term terms interchanged, and transposed. I have always referred back to my truth, EIA-649, Standard for Configuration Management, and they have Configuration Change Management as one of the 5 areas of Configuration Management, making it an activity of the discipline.
“Change Management” is a broader term because it can encompass change across an enterprise, and how to manage that change (e.g, managing change that comes with reorganization) and may have nothing to do with engineering design changes. So I personally never use the term “change management” but refer instead to “configuration change management” which distinguishes a CM activity vs. an enterprise activity.
Praveen Malik says:Hi Cheryl, Thanks for your comment. Here I have used change management in the context of project management and not for enterprise change management.